Major projects we completed
Projects
Projects
Major Projects we Completed
Cochin Shipyard Ltd
- Project Size: 50 KW
- Type: Grid Tie with Monitoring System
- Date of Completion: March 2016
- Location: Cochin
The project was to carry out the power production through solar plant to cater the partial power requirement of the Naval Dockyard Building situated inside the Shipyard compound. The power produced from the solar power plant consisting of 200 modules of 250 Wp modules is connected to three different PCUs with aggregate capacity of 50 KW (20 KW+20 KW+ 10KW) and the AC power is fed to one of the 22 power station available in the entire premises of Cochin Shipyard Ltd
Usage optimization and structuring running load reduction.
- Project Size: 30 KW
- Type: Grid Tie with Monitoring System
- Date of Completion: Nov 2015
- Location: Trivandrum
The project was to carry out the power production through solar plant to cater the partial power requirement of the Training Campus situated along with headquarters. The power produced from the solar power plant consisting of 120 modules of 250 Wp modules is connected to single PCU of 30 KW and the AC power is fed to the LT 7A connection provided by KSEB Ltd
Cochin Shipyard Ltd
- Project Size: 50 KW
- Type: Grid Tie with Monitoring System
- Date of Completion: March 2016
- Location: Cochin
The college solar plant project powers the entire campus, which includes facilities for over 1000 students, numerous classrooms, 6 science labs, 2 computer labs, and office/staff areas, spread across nearly 5 acres. This solar system handles all lighting, sewage motors, and water pumps without needing a diesel generator or much grid power. The solar power is connected through six single-phase PCUs to the main ACDB panel with input and output controls. A 24-unit battery bank supports the system at night. The structure is designed to withstand wind speeds up to 150 KMPH, suitable for the hilltop campus location.
GoodEarth RiverSong
- Project Size: 40 KW
- Type: Off-Grid
- Date of Completion: Dec 2015
- Location: Calicut
The project was to carry out the power production through solar plant to cater the common amenities power requirement of the Luxury Township built near the Main Byepass. The township consist of close to 28 Flats 6 Villas with facilities like Swimming Pool, Lift , Gym Club Area etc. The entire common facilities along with lighting , sewage motors and water pumps are operated through the solar power plant even without the diesel Generator back up and the consumption of Grid Power since its inception is NIL. The power produced from the solar power plant is connected to a three phase PCU is connected to the main ACDB panel with input and output controls. The battery bank of 96 units supports the entire system during the night time and the structure built is designed to provide a leak proof area so that the tenants can use the space under the solar plant as their during yard.